Electric Vehicle Charging

Electric Vehicle Charging is Getting an Upgrade!

McClellan Park TMA will be upgrading its EV charging program with Chargepoint Dual Level II Chargers. The program will be expanding to 12 chargers throughout the business park. Using a mobile app, you will be able to quickly find a charging station, schedule a time to charge, and track your usage and spending. Below is a construction schedule with locations and estimated dates of completion:

  • Luce and Peacekeeper Replacements – 9/4/19 (charging not available 8/29 – 9/4)
  • McClellan Conference Center Replacements – 9/11/19 (charging not available 9/4 – 9/11)
  • Howard and Dudley – 10/29/19
  • Lions Gate Hotel – 11/5/19
  • Luce and Peacekeeper (additional chargers) – 11/12/19
  • Dudley and Forcum Parking Lot – 12/10/19